Originally posted July 7, 2008
We're just a few weeks away from completion. Here's the latest update from Parks and Recreation. More updates can be found in the files section of theFirst Run newsgroup.
Again, thanks for your patience. There was a lot of activity going on behind the scenes even when it looked like work wasn't taking place at the construction site. The delays have involved finding the right materials to create the smooth, dust-free, paw-friendly surface that will be installed next week. The suppliers recently located a nicer material called "Plymouth Brown Mix" and Parks rushed to test and acquire this.
They've also taken extra time with this job to develop a set of standards and best practices for future dog run constructions. Yes, its caused some delay but with new standards in place it will provide for better upkeep and repairs down the line. And frankly, we've probably got the only Parks Dept in the country that cares about building better dog parks. One of the reasons that makes New York City Deptartment of Parks & Recreation the very best.
July 7, 2008
From: New York City Department of Parks & Recreation
All of the necessary paper work has been completed for the ordering of the Plymouth Brownstone Screenings. Delivery of the material is set to begin at the latest next Monday. Ten loads, one per day, will be stockpiled north of the run. After the first half of the material is delivered, the contractor will lay the last layer of geotextile fabric over the bottom layer of broken stone and begin to spread the screenings. That should take a total of two weeks.When that work is completed on the projected date of July 28, the benches and picnic tables will be placed. Barring any unusual rain delays, the run should be open by July 30., 2008